What a Curb and Gutter Contractor's Bid Should Include
By Dean Hollier. Updated October 2026.
A complete concrete curb and gutter bid names every scope item: layout, subgrade, joints, curing, inlets, ramps, backfill, testing, traffic control, and permits. It states a pay unit for each line, usually the linear foot for curb, as TxDOT Item 529 does. It also lists exclusions in writing, so two bids can be compared line by line.
The Short Answer
A good curb and gutter bid tells you exactly what you are buying. It lists each scope item, the unit it is paid in, the quantity, and what is left out.
Bids that skip those details look cheaper on paper. The gap shows up later as change orders for soft subgrade, extra hand work, or traffic control nobody priced.
This guide is for developers comparing subcontractors, general contractors assembling a bid package, and property owners replacing a damaged run. It covers what to look for, not what anything should cost.
Scope Items Every Bid Should Name
- Layout and stakes: Say who sets line and grade stakes and who furnishes the flow-line elevations. Restaking after another trade knocks stakes out can turn into a dispute.
- Subgrade preparation: Item 529 has the contractor shape and compact the curb foundation to plan. The bid should say whether soft-spot repair is in or out.
- Forming or slip-form: State which runs are machine-placed and which are hand-formed. For hand-formed curb, Item 529 caps each placement at 50 feet unless an exception is approved.
- Concrete mix: Name the concrete class or strength. TxDOT's default for curb is Class A concrete, though the plans may require another material.
- Reinforcement and dowels: List the steel, any fibers, and any dowels drilled into existing curb. Item 529 lets fibers replace steel in Class A concrete unless the plans prohibit it.
- Joints: Confirm contraction and expansion joint spacing, any sealant, and how the curb joints line up with the paving joints.
- Curing: State the curing method and how long it lasts. On TxDOT work, curb cures for no less than 72 hours.
- Inlets and tie-ins: Note whether the curb crew forms into inlet boxes, driveways, and existing curb, and who sets inlet tops to final grade.
- Ramps and transitions: Curb ramps, returns, and full-to-flush transitions are hand work. Public bid forms often price ramps per each, by ramp type.
- Backfill: Say who backfills behind the curb, with what material, and when. Curb left unbacked can be undercut by the first hard rain.
- Cleanup: Include concrete washout, haul-off of spoils and broken concrete, and a final sweep of the gutter line.
- Testing and inspections: Say who hires the testing lab and who pays for retests. Name the city or county inspections the schedule depends on.
- Traffic control: If the work touches a public street, include the signs, barricades, and flaggers that the traffic control plan requires.
- Permits: Identify who pulls each permit. Beaumont requires its Street Cut and Barricading permit for lane closures, barricades in the street, and street cuts.
How TxDOT Measures and Pays for Curb
Many public curb jobs in Texas follow the TxDOT Standard Specifications. Jefferson County, for one, requires subdivision roads to meet the current edition.
Item 529 is the TxDOT item for concrete curb, gutter, and combined curb and gutter.
Item 529 measures curb by the foot, which means linear feet along the run. Payment uses one of three bid items, Concrete Curb, Concrete Curb (Mono), or Concrete Curb and Gutter, at the unit price bid.
That unit price is full compensation for surface preparation of the curb foundation, plus equipment, labor, materials, tools, and incidentals. Shaping the grade under the curb is not its own pay line.
Removal is a separate item. TxDOT Item 104 measures removed curb and curb and gutter by the foot in its original position. Its price covers breaking, loading, hauling, and disposal.
Item 104 also calls for saw-cutting to neat lines. Concrete the contractor damages that was meant to stay gets replaced at no cost to the owner.
Private bids do not have to follow TxDOT. These definitions still make a useful yardstick when you ask a bidder what each line includes.
Concrete curb and gutter services · Curb repair and replacement
Unit Price Versus Lump Sum
A unit-price bid sets a rate per foot, square yard, or each. You pay that rate times the quantity actually built or measured.
A lump-sum bid sets one total for a defined scope. The contractor carries the risk of quantities running over, and the owner carries the risk of a loosely written scope.
Unit prices suit work where quantities may shift, such as curb replacement along an aging street. Lump sums suit fixed scopes drawn on complete plans.
Public curb bids often mix the two. TxDOT Item 500 measures mobilization by the lump sum or by each, and Item 502 measures barricades, signs, and traffic handling by the month.
Read the arithmetic rules as well. Jefferson County's bid for its 2024 Concrete Road Repair Project said the unit price governs when it conflicts with the extended total.
The City of Elgin's bid form for a downtown sidewalk project, bid in January 2022, had prices written in words and figures. When the two disagreed, the words controlled.
That form also said any work in the specifications falls under one of the listed items, even if no item names it. Ask each bidder where that unnamed work was priced.
What a Public Bid Schedule Looks Like
| Bid item | Typical pay unit | Where it appears |
|---|---|---|
| Concrete curb and gutter | Linear foot | TxDOT Item 529; Elgin bid form |
| Curb transition, full to flush | Linear foot | Elgin bid form |
| Removing concrete curb | Linear foot | TxDOT Item 104; Elgin bid form |
| Removing sidewalk | Square yard | TxDOT Item 104; Elgin bid form |
| Curb ramp, by type | Each | Elgin bid form |
| Precast curb inlet | Each | Elgin bid form |
| Lime or cement treatment | Square yard | TxDOT Items 260 and 275 |
| Lime or cement material | Ton | TxDOT Items 260 and 275 |
| Mobilization | Lump sum | TxDOT Item 500; Elgin bid form |
| Traffic control | Month | TxDOT Item 502; Elgin bid form |
| Storm water pollution prevention | Lump sum | Elgin bid form |
Quantities and units come from the plans. If a private bid uses different units, ask the bidder to convert them so the bids line up.
Common Exclusions to Read Closely
- Survey and staking: Many curb bids assume the owner's surveyor sets control and grade stakes.
- Soft or unsuitable subgrade: Undercut and replacement of wet or weak soil is often excluded or carried as an allowance. TxDOT Items 260 and 275 charge soft-spot correction to the contractor only when that contractor built the subgrade.
- Lime or cement treatment: Stabilization is usually its own scope, measured by the square yard of treated area.
- Storm sewer and inlets: The curb crew may form into inlet structures that another trade sets and adjusts.
- Testing fees: Density tests, concrete cylinders, and retests after a failure may sit outside the bid.
- Permit and inspection fees: Some bids leave permit costs and fees to the owner.
- Traffic control beyond cones: Lane closures run under a traffic control plan are often left out of small bids.
- Restoration: Sod, landscaping, irrigation repair, and driveway or walk panels outside the curb line.
- Utility conflicts: Moving a valve box, meter, or service line found in the curb line.
- Remobilization: Extra trips when the site is not ready or rain pushes the work back.
Questions to Ask Before You Sign
- Which plans did you bid? Confirm every bidder priced the same plan revision and the same addenda.
- How was footage counted? Ask whether curb footage runs through driveways, inlets, and ramps or stops at them.
- What does subgrade work include? Ask about compaction, moisture control, proof rolling, and who pays for soft spots.
- Machine or hand-formed? Ask which runs go on the slip-form machine and which are formed by hand.
- What protection is included? Ask about curing compound, rain covers, and keeping traffic off fresh curb.
- Who handles inspections? Ask who books city or county inspections and who stands by for them.
- How are changes priced? Ask how added or deleted footage and extra hand work will be paid.
- What is excluded? Get the exclusion list in writing and attach it to the contract.
Comparing Bids Side by Side
Lay the bids out on one sheet with the same item list and units. Give each excluded item its own row so missing scope stands out.
Then check the assumptions behind the schedule. A low number that assumes firm, dry subgrade may not hold up on a Southeast Texas clay site.
Hollier Construction Services, a Beaumont concrete contractor, is family-owned and now in its third generation. The company owns and operates a slip-form curb machine and builds to the TxDOT and city specifications the plans call for.
Its own crews also clear land, stabilize soil, prepare sites, pave, and pour sidewalks. One bid can then cover the whole concrete package, anywhere in Jefferson, Orange, or Hardin County.
To request a bid, phone (409) 718-5701 or write to dean@hollierconstructionservices.com. The office keeps Monday to Friday hours, 9 AM to 5 PM.
Subdivision curb and gutter · Soil stabilization · Land clearing · Concrete paving · Subgrade prep on Southeast Texas clay · Request a bid
Sources
Official sources used for this article:
TxDOT: 2024 Standard Specifications, Item 529 Concrete Curb, Gutter, and Combined Curb and Gutter · TxDOT: 2024 Standard Specifications, Item 104 Removing Concrete · TxDOT: 2024 Standard Specifications, Item 500 Mobilization · TxDOT: 2024 Standard Specifications, Item 502 Barricades, Signs, and Traffic Handling · TxDOT: 2024 Standard Specifications, Item 260 Lime Treatment (Road-Mixed) · TxDOT: 2024 Standard Specifications, Item 275 Cement Treatment (Road-Mixed) · City of Elgin, Texas: Addendum No. 1 and Section 00400 Bid Form, 2020 Main Street Program Downtown Sidewalk Improvements · Jefferson County, Texas: IFB 24-058/MR, Jefferson County 2024 Concrete Road Repair Project · Jefferson County, Texas: Subdivision and Development Regulations (Amendment No. 11, March 2026) · City of Beaumont: Frequently Asked Questions, Public Works (Engineering)
Frequently asked questions
How is concrete curb and gutter usually priced?
Most bids price it per linear foot of a named profile. TxDOT Item 529 measures curb by the foot and pays the unit price bid for the specified curb type.
Is subgrade preparation included in the curb price?
Under TxDOT Item 529, preparing the curb foundation is part of the curb unit price. Lime or cement treatment and soft-spot repair are often separate lines, so check each bid.
Should I choose a unit-price or lump-sum bid?
Unit prices fit work where quantities may change, such as repairs on an older street. A lump sum fits a fixed scope with complete plans. Many public bids combine both.
Why do curb ramps show up as separate bid items?
Ramps are formed by hand and built to accessibility details, so they take more labor than straight curb. Public bid forms often list them per each, by ramp type.
Who should pay for testing?
The contract should say. On TxDOT treated subgrade, the Engineer samples and tests density and moisture. On private work, put in writing who hires the lab and who pays for retests.
Do I need a permit for curb work on a city street?
Usually. In Beaumont, a lane closure, barricades in the street, or a street cut calls for a Street Cut and Barricading permit. Grading that disturbs 450 square feet or more needs a grading permit application first.