Subdivision Curb & Gutter Contractor in Southeast Texas

Hollier Construction Services lays machine-formed concrete curb and gutter for subdivision phases across Southeast Texas, working for developers and homebuilders. Its slip-form machine runs street curb once utilities and subgrade are ready. Hand-form crews finish the radii and ADA curb ramps so the paving crew can follow without waiting.

Where Curb Falls in the Phase Sequence

On a new subdivision street, curb is the hinge between dirt work and paving. Underground utilities go in first, then the subgrade is built and checked, then the curb, then the pavement.

Holding that order protects the concrete. A missed service line found after curb is down means saw-cutting brand-new work.

Some designs use integral curb, placed with the pavement instead of ahead of it. ACPA's intersection jointing method is written to work with integral or separate curb and gutter. The plans decide which a street uses.

In Beaumont, the Engineering division reviews, inspects, and approves all subdivision site development plans for compliance with city specifications and codes. Street design must also follow the city's official street construction standards.

Jefferson County's subdivision rules require roads built to the most current TxDOT Standard Specifications. On TxDOT-detailed work, the CCCG-22 sheet points to Item 529 for curb and gutter materials and construction.

Stringline and Grade Control

A slip-form curb machine follows a stringline. Sensors riding on the line steer the mold for both alignment and elevation.

Stakes go closer together on curves than on straight runs. The line is kept tight and checked through the day.

A line that gets bumped is reset immediately, or the bump shows up in the finished concrete. The stakes themselves come from the engineer's flow-line elevations and are checked before the machine starts.

The subgrade trimmer should work from the same line, so the curb sits on a uniform base. A high spot left in the grade becomes a thin spot in the curb.

Inlet Tie-Ins and Flow Lines

Curb inlets are where machine work stops and hand work starts. The inlet structure is set first, and the curb on each side is hand-formed into it at the plan elevation.

Every flow line has to fall toward an inlet. TxDOT's Hydraulic Design Manual says gutter slopes on curbed pavement should usually be at least 0.3 foot per 100 feet.

The manual admits that minimum can be hard to hold in places. There, a rolling or sawtooth gutter profile may be needed, and the curb has to follow it exactly.

ACPA's street jointing guide covers joints near drainage structures. When a contraction joint lands within 5 feet of a catch basin or manhole, nearby panels can be shortened or skewed to meet it.

Pipe standards come from the city. Beaumont's engineering FAQ says storm sewer pipe in city right-of-way must be reinforced concrete pipe or high-performance polypropylene.

Beaumont's code also lays out the street right-of-way. Storm sewer runs one and a half feet behind the curb. Buried utilities sit at least 24 inches below the top of curb or pavement.

Production Planning With a Slip-Form Machine

Hollier owns and operates its slip-form machine. Under typical conditions it places several hundred linear feet in a working day. Its profiles include barrier and roll curb plus valley gutter.

That pace holds only when the site is ready. The machine needs a continuous trimmed path, steady concrete delivery, and a finishing crew jointing behind it.

Plan long, uninterrupted runs between intersections. Each gap left for an unset inlet or an open utility crossing means another setup and more hand work.

Radii, Curb Ramps, and Hand Work

Tight returns at intersections, cul-de-sac bulbs, and ADA curb ramps are formed by hand. Those pieces go in alongside the machine runs, built by Hollier's hand-form crews.

Ramps take the most care. Slopes, landings, and detectable warning surfaces must match the plans and the accessibility standard the city enforces.

Beaumont's code fixes several of the dimensions crews build to. A residential street is 26 feet between curb faces, and a permanent cul-de-sac bulb has a 33-foot pavement radius.

Profile choice also shapes the homebuilding stage. Beaumont permits roll-type curb on its residential streets, which lets each driveway cross with no cut. Barrier curb needs an opening at every lot.

Inspections, Weather, and Gulf Coast Clay

Ask the city at the preconstruction meeting which stages need an inspection. Pouring ahead of a required check can mean removing good concrete.

Soil drives the schedule here. NRCS describes the Beaumont soil series as very deep, poorly drained, and very slowly permeable. It formed in clayey sediments on the Beaumont Formation.

The series is classed as smectitic clay, and its subsoil shows slickensides, the polished faces left by soil movement. NRCS notes that dry Beaumont soil cracks open half an inch to over an inch wide and a foot or more deep.

After a heavy rain, a clay subgrade can stay too wet to trim or carry the machine for days. TxDOT's soil treatment guidelines say lime treatment of elevated-plasticity soils can reduce shrink-swell and give crews a working platform.

Stabilizing the subgrade, where the plans call for it, gives the curb a firmer base. Hollier self-performs soil stabilization, which keeps that step in-house.

Heat brings the opposite problem. Fresh concrete loses surface water quickly, so curing compound or plastic sheeting goes on promptly to slow evaporation. Build rain days into the phase schedule as well.

When should the curb crew be scheduled in a subdivision phase?

After underground utilities are installed and the subgrade has been built, checked, and trimmed. Booking the curb machine before that work is finished usually means idle time or broken runs.

How much curb can a slip-form machine lay in a day?

Under typical conditions, Hollier's machine covers several hundred linear feet in a day. Actual output depends on site readiness, concrete delivery, the number of inlets and radii on the street, and the weather.

Who reviews new subdivision streets in Beaumont?

The City of Beaumont's Engineering division reviews, inspects, and approves subdivision site development plans. Ask early which stages need a city check so the crew never pours ahead of one.

How does rain affect the curb schedule?

Rain hits the subgrade harder than the concrete. Beaumont-series clay drains very slowly, so a wet grade may need several dry days before it can be trimmed and run. Plan weather days into the phase.

Can curb go in before the storm sewer is finished?

It is better not to. Inlets should be set to final elevation first so the curb can be formed into them at the right grade. Gaps left for unfinished inlets break the machine's run and add hand work.

Do you build the curb ramps and cul-de-sac radii too?

Yes. ADA curb ramps and tight radii are hand-form work for Hollier's crews, while the machine lays the straight and gently curved runs. Both are scheduled together so the phase is ready for paving.

Can Hollier also handle clearing, stabilization, and paving?

Yes. Clearing, stabilization, site prep, and paving are all done by Hollier's own crews, so the curb sits inside one concrete package. Fewer trades on a phase means fewer hand-offs.

Should a new subdivision use barrier curb or roll curb?

The engineer and the reviewing agency decide, based on street type and drainage design. In Beaumont, the code allows roll-type curbs on residential streets. Roll curb lets a drive cross with no cut, while barrier curb needs an opening at every drive.

City of Beaumont: Public Works (Engineering division)

City of Beaumont: Frequently Asked Questions, Public Works (Engineering)

City of Beaumont Code (eCode360): Article 26.03, General Design Principles and Specific Design Standards and Improvement Requirements

Jefferson County: Subdivision and Development Regulations (amended March 2026)

USDA NRCS: Official Soil Series Description, Beaumont Series

TxDOT: Treatment Guidelines for Soils and Base in Pavement Structures (August 2019)

TxDOT Hydraulic Design Manual: Section 4, Pavement Drainage (Longitudinal Slopes)

ACPA Wiki: IS061 - Design and Construction of Joints for Concrete Streets

ACPA Wiki: Joint Layout

TxDOT Standard Sheet: Concrete Curb and Curb and Gutter (CCCG-22), referencing Item 529