Hollier Construction Services repairs and replaces broken, settled, and deteriorated concrete curb and gutter across Southeast Texas. Hand-form crews saw-cut out failed sections, rebuild the subgrade, and pour new curb that matches the profile and flow line on either side. The service is for property owners, managers, HOAs, and general contractors in Beaumont, Port Arthur, Orange, and across Jefferson, Orange, and Hardin counties.
Curb problems fall into two groups. Some are local defects in curb that is otherwise sound. Others mean the run has failed, and a patch only delays the next call.
Settlement is the clue that matters most. When a gutter pan sinks, water sits against the joint and soaks the base below. A surface patch cannot fix that. The section has to come out so the subgrade can be rebuilt.
Replacement follows a fixed order. Each step protects the curb that stays in place.
On TxDOT work, Item 529 of the 2024 Standard Specifications covers concrete curb and gutter. It calls for subgrade shaped and compacted to the line, grade, and cross-section on the plans. It limits conventionally formed curb to 50-foot sections unless otherwise approved, and requires at least 72 hours of curing. Changes in curb grade and alignment may not exceed 1/4 inch between any two contacts on a 10-foot straightedge.
A good repair disappears into the block. That means matching the height, face shape, gutter width, and top edge of the curb beside it.
Crews measure the neighboring curb at both ends of the cut before setting forms. Barrier curb, roll curb, and older custom shapes each need forms built to their own profile. Where a city standard detail applies, the replacement follows that detail instead.
Hollier's hand-form crews handle curb repairs, radii, and driveway transitions. Its slip-form machine lays longer runs of barrier curb, roll curb, and valley gutter. A few panels between driveways are hand-form work.
Curb and gutter is part of the storm drainage system. During a replacement, runoff still needs a path to the inlet. Crews keep that path open where they can, or schedule the cut for a dry window.
Public streets need traffic control. In Beaumont, work that partly or fully closes a public right-of-way needs a Street Cut and Barricading permit, with a few exemptions. Contractors apply through the city's Cityworks online permit portal. Parking lots and private drives usually rely on cones, signs, and a phased plan.
Rain moves the schedule more than anything else. Soaked clay loses strength and pumps under a compactor. Pouring on it invites the same settlement that caused the failure. The better plan is to let the base dry and pass compaction first. Item 529 does call for lightly sprinkling the subgrade just before placement, which is very different from a flooded trench.
Ownership decides who pays, who approves the work, and which standard applies. Curb inside a parking lot, a private drive, or an HOA-owned street belongs to that owner. Curb along a public street sits in the public right-of-way.
In Beaumont, the Streets and Drainage Division of Public Works maintains the city's streets and right-of-way. A bond proposal the city posted in July 2026 lists curb and gutter repairs under its street improvements, alongside base repairs and resurfacing.
Residents report street problems by dialing 311, through the Beaumont 311 app, or at 409-980-8311 from outside the city. 311 forwards an investigation request to the department and assigns a reference number for tracking. For street repairs, the city's FAQ gives an expected response of 1 to 3 days, depending on call volume. Concrete panels take longer.
Private work in the right-of-way still needs city approval. Beaumont's driveway permit sheet requires a permit for any construction, including removal, in the public right-of-way. It also says the city replaces driveways destroyed, altered, or removed by a city project. City code places driveway and sidewalk upkeep on the owner or lessee of the property served. Before an owner or HOA pays for street curb, confirm with the city which side of that line the damage falls on.
Hollier is a family-owned, third-generation concrete contractor with its home base in Beaumont. Crews work daily across Jefferson, Orange, and Hardin counties and build to the TxDOT and municipal specifications on the plans. Because Hollier also pours sidewalks, flatwork, and paving, a cracked apron or walk panel beside the curb can be handled by the same contractor. Dean answers at (409) 718-5701 and dean@hollierconstructionservices.com on weekdays, 9 AM to 5 PM.
Check the gutter line first. A section that has sunk, tilted, or holds water needs replacement down to the subgrade. Isolated chips or one cracked panel on curb that still drains can often be fixed locally.
The Streets and Drainage Division of Public Works maintains Beaumont's streets and right-of-way. Under city code, driveways and sidewalks are the responsibility of the owner or lessee of the property they serve. Call 311 to confirm who owns the damaged piece before hiring anyone.
In Beaumont, yes. The city requires a permit for any construction or removal in the public right-of-way. Work that closes part of the right-of-way also needs a Street Cut and Barricading permit. Other cities have their own permit rules, so check with the local engineering or public works office first.
It should match in shape. Crews measure the curb on both sides of the cut and set forms to the same height, face, and gutter width. Fresh concrete rarely matches the color of weathered curb right away, so expect a visible difference at first.
Dowels tie the new pour to the existing curb on each side. They help keep the joint aligned so one piece does not drop or lift on its own. Whether dowels are required depends on the plans or the city's standard detail.
It depends on the mix, the weather, and the specification. TxDOT Item 529 requires at least 72 hours of curing for curb on state work. Keep vehicles off until the contractor confirms the concrete is ready for load.
Not if the subgrade is saturated. Wet clay loses strength and will not compact properly, so the pour waits until the base dries. Pouring on a soft base risks repeating the settlement that caused the original failure.
If the HOA owns the streets, the curb is the HOA's to maintain and replace. If the streets were dedicated to a city or county, that agency typically controls the work. Check the recorded plat or ask the city before planning the project.
TxDOT: 2024 Standard Specifications, Item 529 Concrete Curb, Gutter, and Combined Curb and Gutter
City of Beaumont: Public Works
City of Beaumont: Frequently Asked Questions, Public Works (Streets & Drainage)
City of Beaumont: Frequently Asked Questions, Public Works (Engineering)
City of Beaumont: Beaumont 3-1-1
City of Beaumont: Read A Detailed List of Planned Projects (News Flash, July 21, 2026)
City of Beaumont: Driveway Construction and Maintenance (Driveway Permit Information PDF)