Scheduling the Curb and Gutter Contractor in a Subdivision Phase

By Dean Hollier. Updated October 2026.

In a subdivision phase, concrete curb and gutter goes in after clearing, underground utilities, and an approved subgrade, and before street paving and sidewalks. Each handoff waits on an inspection or test, so the schedule follows approvals as much as crews. Cure times, rain on clay, and joint layout shared with the paving crew decide the rest.

The Order of Work in a Phase

Approvals Before the First Crew Mobilizes

Inside Beaumont, Article 26.02 of the city code requires construction plans signed off by a registered professional engineer. They go to the city engineer before work begins on proposed streets.

Those plans show street cross-sections, drainage slopes, pavement details, and dimensions and specifications for curbing. Any portion the city engineer finds below standard cannot start until it is corrected.

Plan review and field inspection both sit with Beaumont's Engineering division, part of Public Works.

Clearing needs its own paperwork. Beaumont requires a grading permit application before clearing, leveling, or other work that will disturb 450 square feet or more.

Outside city limits, Jefferson County's subdivision regulations set the order. Plat and plans are submitted, the preliminary plat is approved, Commissioners Court approves the final plat and plans, and the record plat is filed.

The county rules add that final plat approval does not by itself authorize construction. Streets may be built after the record plat is recorded, with construction and maintenance security posted under Section 7.

Where land sits in a city's extraterritorial jurisdiction, both sets of rules may apply. The county says the stricter standard governs and that city approval generally comes before final county review.

In Beaumont's planning area, the city code hands streets to the county. Jefferson County standards and the county engineer govern design, construction, and acceptance there.

Land clearing · Subdivision curb and gutter

Inspections That Gate Each Step

StepGate before moving onSource
Clearing and gradingInitial grading inspection at startBeaumont FAQ
Storm sewer tie-insInspection before backfill in city right-of-wayBeaumont FAQ
SubgradeApproval before any base is placedJefferson County, earlier edition
Sub-base and basePI, density, and base depth testsJefferson County, earlier edition
CurbAt least 72 hours of curingTxDOT Item 529
Final gradingInspection once permanent erosion control is inBeaumont FAQ
Utilities and drainageAs-built plans filed with the city engineerBeaumont Article 26.02

Inspection points change with the jurisdiction and the plans. Confirm the full list at the preconstruction meeting.

How Jefferson County Ties Inspections to Acceptance

Jefferson County's definition of a public road subdivision says its roads and drainage enter the county system once a one-year maintenance period is approved.

The county's earlier edition spelled out the inspection chain. The developer had to coordinate every inspection and lab test with the Precinct Commissioner or a designated agent.

That edition barred starting the next phase until the required inspections and tests were obtained. It also said no base goes on a street until the subgrade is approved.

Its acceptance step called for a final inspection no earlier than 30 days before Commissioners Court acted, with a report recommending acceptance.

Amendment No. 11, adopted in March 2026, updated the road design criteria and the maintenance requirements. Ask the County Engineer which inspections apply now before you set dates.

Weather and Cure Time

New curb needs time before the paving crew works against it. On TxDOT-specified work, Item 529 keeps curb under cure for 72 hours or longer.

Treated subgrade adds its own wait. Lime-treated soil under Item 260 needs a minimum of two to five days, depending on PI. Item 275 cures cement-treated soil for at least 3 days.

Rain usually costs more days than curing does. Because Beaumont-series clay has very slow permeability, a soaked street section may sit idle until it dries back to optimum moisture.

Cold fronts can pause treatment too, since both TxDOT items set a minimum air temperature for spreading lime or cement.

Plan float. A phase schedule with no weather days pushes every later trade back when the first storm arrives.

Cure time before traffic · Subgrade prep on Southeast Texas clay

Coordinating Curb and Paving Crews

The curb and paving crews share joints, grades, and sometimes concrete. Under Item 529, each transverse curb joint copies the type and position of the pavement joint beside or beneath it.

Settle the joint layout before the curb machine runs. Expansion joint material extends through the curb and matches the thickness and type used in the pavement.

Curb poured monolithically with the street takes the pavement's concrete class under Item 529, so both crews order the same mix.

Utility depth affects the curb line. Beaumont buries underground utilities no less than 24 inches, measured from the top of curb or pavement. Its layout places storm sewer 1.5 feet behind the curb.

Plan the hand-form crew alongside the machine. Inlet tie-ins, intersection returns, and ramps should be finished before paving starts on that block.

Hollier's own slip-form machine places valley gutter, barrier curb, and roll curb, and the same company self-performs concrete paving. One contractor can then sequence curb and street without a handoff.

Concrete paving · Concrete curb and gutter

Sidewalks and Lot Work

Sidewalks often come last, and Beaumont ties them to each lot. Under Section 26.03.004, a building permit includes any sidewalk required for that lot.

The sidewalk must be installed before the final building inspection. No certificate of occupancy is issued until the lot's sidewalk requirements are met.

If a lot is not developed within five years after the final plat is recorded, the current owner must build the sidewalk.

On residential lots, width depends on placement. A walk set 2 feet or more behind the curb needs at least 4 feet of width. One built at the back of curb needs at least 5 feet.

In Beaumont's planning area, the same section says sidewalks are not required.

Punch List Before Acceptance

Acceptance and the Months After

In Beaumont, the city council accepts dedicated streets and utilities. Article 26.02 says planning commission approval of a plat does not mean the city has accepted its streets.

In Jefferson County, the earlier edition kept the developer responsible for street and drainage maintenance for at least one year. Recording the plat or dedicating right-of-way did not count as county acceptance.

Plan for repairs in that window. Curb cracked by construction traffic or settled at a utility trench is easier to fix before acceptance than after.

Hollier, a family-owned contractor in its third generation, works from Beaumont across Jefferson, Orange, and Hardin counties. Clearing, soil stabilization, and site preparation are handled by its own crews as well.

Phase planning calls go to (409) 718-5701, and email goes to dean@hollierconstructionservices.com. Office hours are 9 AM to 5 PM, Monday through Friday.

Subdivision curb and gutter · Soil stabilization · Land clearing · What a curb bid should include · Contact Hollier

Sources

Official sources used for this article:

Jefferson County, Texas: Subdivision and Development Regulations (Amendment No. 11, March 2026) · Jefferson County Drainage District No. 3: Jefferson County Subdivision and Development Regulations (earlier edition, amended through January 2022) · City of Beaumont, TX Code: Article 26.02, Procedure and Plat Requirements · City of Beaumont, TX Code: Article 26.03, General Design Principles and Specific Design Standards and Improvement Requirements · City of Beaumont: Public Works · City of Beaumont: Frequently Asked Questions, Public Works (Engineering) · TxDOT: 2024 Standard Specifications, Item 529 Concrete Curb, Gutter, and Combined Curb and Gutter · TxDOT: 2024 Standard Specifications, Item 260 Lime Treatment (Road-Mixed) · TxDOT: 2024 Standard Specifications, Item 275 Cement Treatment (Road-Mixed) · USDA NRCS: Official Series Description, Beaumont Series

Frequently asked questions

Can curb go in before the subgrade is inspected?

It should not. Jefferson County's earlier rules barred base placement until the subgrade was approved, and Item 529 expects the curb foundation compacted to plan before concrete. Pouring early risks tearing out good curb.

How long does curb need before paving starts?

Item 529 sets a 72-hour minimum cure on TxDOT work. The paving crew also needs backfill done and the joint layout agreed, so allow time beyond the cure itself.

Who accepts new subdivision streets in Beaumont?

The city council accepts dedicated streets and utilities. Planning commission approval of the plat is not acceptance, and as-built plans must be filed with the city engineer.

When does Jefferson County take over subdivision roads?

County maintenance starts when the roads and drainage of a public road subdivision are accepted, after an approved one-year maintenance period. Ask the County Engineer about current inspection steps under the 2026 amendment.

Are sidewalks built along with the streets?

Often not. In Beaumont, each lot's building permit covers its sidewalk, and the walk must be finished before the final building inspection. The city's planning area does not require sidewalks.

What slows a curb schedule most in Southeast Texas?

Rain on clay subgrade. Beaumont-series soils are poorly drained, so wet grades can idle crews for days at a time. Build weather days into the phase plan from the start.