Beaumont Driveway Curb Cut Permits: A Local Contractor Answers

By Dean Hollier. Updated October 2026.

Yes. The City of Beaumont requires a permit before anyone builds, rebuilds, repairs, or alters a driveway or sidewalk. A curb cut is part of the driveway approach, so it is covered. The Engineering Department approves the location and design, and the Building Codes Division issues the permit. A city inspector checks the forms before concrete is placed.

The Short Answer

Yes, cutting a new driveway into a Beaumont curb needs a city permit. Section 14.03.091 of the Code of Ordinances requires one before any driveway or sidewalk is constructed, reconstructed, repaired, or altered.

The city's driveway permit sheet goes further. It says any construction in the public right-of-way needs a permit. It also notes that the city owns the street and the property on each side, so the approach behind the curb is city right-of-way.

The code names one exception: driveways and sidewalks built as part of a city street paving or widening contract. Approaches built under that contract do not need a separate driveway permit. Everyone else applies first, from a homeowner widening a drive to a developer opening a commercial entrance.

Who Issues the Permit

Two city offices are involved. The city engineer must approve the location and design, and the city's FAQ says the Engineering Department approves the permit. The Building Codes Division then issues it. The FAQ also says applications are made online.

The code limits who may apply. Under Section 14.03.092(b), the applicant must be the owner or lessee of the abutting property, or a contractor representing them. Section 14.03.091 also holds the permit until a filing that Section 14.03.053 requires of contractors is on record. Ask Building Codes what applies to yours.

The application needs a scaled drawing. It shows the address, the lot and block if platted, the driveway width, and the drive's position relative to property lines and neighboring drives.

Section 14.03.093 applies the driveway fee in the city's fee schedule, on top of any building permit fee. On timing, the code and the permit sheet differ. Section 14.03.091 voids a permit if the driveway is not built within six months of issuance. The permit sheet says that if work begins within six months, the permit is good for one year.

For questions, the permit sheet lists the Public Works Engineering Division at (409) 880-3725. The city's Building Codes page lists (409) 880-3100.

What the Rules Cover

RuleWhat the city sources stateSource
Minimum width10 feet for residential drives; 15 feet for one-way and 20 feet for two-way commercial drivesSec. 14.03.058(b)(7); permit sheet
Maximum width35 feet for commercial or public establishments; approaches for vehicle docks or vehicle doorways may reach 60 feetSec. 14.03.058(c); permit sheet
Distance from an intersectionNo curb cut within 30 feet of the extended curbline or edge of pavementSec. 14.03.058(b)(2); permit sheet
Corners with sidewalksThe approach may not begin closer to the corner than the inside edge of the sidewalk on the intersecting streetSec. 14.03.058(b)(3)
Spacing between drivesCode: a safety island at least 20 feet wide. Permit sheet: 10 feet residential, 20 feet commercial, 30 feet commercial on arterialsSec. 14.03.058(b)(5); permit sheet
Side property lineNearest drive edge at least 5 feet (residential), 10 feet (commercial), or 15 feet (commercial on arterials) from it, or the setback line if greaterPermit sheet
AngleBetween 45 and 90 degrees to the street centerlineSec. 14.03.058(b)(4)
Number of drivesUp to two on 100 feet of frontage or less, three under 300 feet, four under 600 feetSec. 14.03.058(d)
Property linesPavement on private property keeps at least 2 feet from interior property lines. The curb tangent point may not extend past the property line.Permit sheet; Sec. 14.03.058(b)(6)-(7)
Minimum radiusDriveway radius of at least 5 feet residential, 10 feet commercial, 15 feet commercial on arterialsPermit sheet
MaterialNew or rebuilt approaches are concrete or asphalt and must meet city street construction standardsPermit sheet; Sec. 14.03.057
CulvertsIf pipe is needed, Public Works sets pipe size and grade after the permit issues; request it 24 hours aheadSec. 14.03.092(a)

This table condenses the ordinance and the city's permit sheet. Where they differ, ask the Engineering Division which figure it will apply before you design a drive near any of these limits.

Materials, Standards, and Other Limits

The permit sheet says new or reconstructed approaches must be concrete or asphalt. It also says they must follow Chapter 14, Article 3 of the code. Section 14.03.057 adds that all materials must meet the city's street construction standards and specifications.

Contractors build to the plans, specifications, and grades furnished by the city engineer. The permit sheet puts the materials and labor for driveways, sidewalks, and culverts on the abutting property owner.

Section 14.03.058 explains the goal behind the geometry. An approach should be located and angled so a vehicle leaving the property can turn into the lane moving in the direction it wants. An approach also may not encroach on municipal facilities.

The permit sheet sets construction minimums too. Driveway concrete is at least 4 inches thick for residential work and 6 inches for commercial. Reinforcement is No. 6 wire mesh or No. 4 rebar at 12 inches on center. Subgrade is compacted to 95 percent of standard Proctor, and concrete must reach 3,000 psi in 28 days. Driveway slope may not exceed 12 percent. Property corners must be exposed before inspection.

How a Curb Cut Is Built

Inspections and Scheduling

City pages use different names for the same two driveway checks. The permit sheet calls them an initial inspection before the pour and a final inspection after construction is complete. The FAQ calls them Driveway Pre-Pour and Driveway Post-Pour. The post-pour check comes after the forms are removed and washout and cleanup are done.

Scheduling instructions vary. The permit sheet says to call 311, and the 311 page says 311 schedules building inspections. The FAQ says you can call 311 or book through the city's Cityworks online permit portal with your permit number. The Building Codes page says permit holders schedule all inspections on the portal, and none by phone.

Ask which method applies when your permit is issued. Either way, the permit sheet says concrete may be poured only after the inspection is approved.

Before You Apply

Check the rules before the drawing is final. A drive placed too close to a corner, or too close to a neighbor's drive, will not meet the code. Size the width to what your vehicles need, and leave the spacing between approaches that the code and permit sheet call for.

If the lot drains to a roadside ditch instead of a curb, the culvert is part of the job. The FAQ says to schedule the Culvert Grade Set inspection before you buy or install the pipe.

Hollier Construction Services builds driveway curb cuts and transitions in Beaumont and across Jefferson, Orange, and Hardin counties. Call (409) 718-5701 or email dean@hollierconstructionservices.com, Monday to Friday, 9 AM to 5 PM.

Driveway curb cuts · Concrete curb and gutter in Beaumont · Curb repair and replacement · Who repairs the curb in front of your house in Beaumont? · Contact Hollier Construction Services

Sources

Official sources used for this article:

City of Beaumont, TX Code (eCode360): Division 2, Sidewalk and Driveway Construction and Maintenance · City of Beaumont, TX Code (eCode360): § 14.03.058 Driveway approaches · City of Beaumont, TX Code (eCode360): § 14.03.057 Materials and labor for construction of driveways and sidewalks · City of Beaumont, TX Code (eCode360): § 14.03.091 Required; bond to be filed; voiding · City of Beaumont Public Works: Driveway Construction and Maintenance (Driveway Permit Information PDF) · City of Beaumont: Frequently Asked Questions, Public Works (Engineering) · City of Beaumont: Building Codes · City of Beaumont: Beaumont 3-1-1

Frequently asked questions

Do I need a permit just to widen my driveway at the street?

Yes. Section 14.03.092(c) bars changing a driveway's dimensions without a permit. The new width still has to meet the minimums and maximums in Section 14.03.058 and the city's permit sheet.

How far from a corner does a Beaumont driveway have to be?

Section 14.03.058 keeps curb cuts at least 30 feet back from the extended curbline or the edge of pavement at an intersection. The permit sheet repeats the 30-foot minimum. Measure from the corner before you settle on a spot.

Can my contractor apply for the permit?

Yes. The code lets the owner or lessee of the abutting property apply, or a contractor representing them. Ask your contractor for the permit number before any curb is cut.

How long is a Beaumont driveway permit good for?

Section 14.03.091 says a permit becomes void if the driveway is not built within six months of issuance. The city's permit sheet says the permit is good for one year if work begins within six months. Confirm the deadline with Building Codes when the permit is issued.

Can the approach be asphalt instead of concrete?

The city's permit sheet allows concrete or asphalt for new or reconstructed approaches. Either way, materials must meet city street construction standards. Hollier's hand-form crews build driveway transitions in concrete.

Is there a fee for a driveway permit?

Yes. Section 14.03.093 applies the driveway fee from the city's fee schedule, in addition to any building permit fee. The FAQ says the fee is paid before the permit is issued. Confirm the current amount with Building Codes.

Do I need a permit if the city is rebuilding my street?

Not for approaches built under the city's own paving or widening contract, because the code exempts that work. Section 14.03.052(c) also has the city replace driveways its roadway work removes. Any separate driveway changes you make still need a permit.