Hollier Construction Services cuts existing street curb and pours concrete driveway approaches across Southeast Texas, including Beaumont, Port Arthur, and Orange. The work suits homeowners adding or widening a drive and businesses opening a new entrance. Crews remove the old curb, rebuild the gutter line, and form the approach and its transitions to the plans and the city's driveway rules.
Every approach begins by removing a stretch of street curb.
TxDOT's Roadway Design Manual says the entire curb and gutter should come out for the length of the cut. The gutter pan is then recast as part of the driveway apron.
A saw-cut removal takes only the width the approach needs and suits curb that is sound and draining. Going back to the nearest joints suits panels that are cracked, settled, or ponding.
TxDOT's current CCCG-22 curb and gutter sheet says existing curbs and driveways being removed are sawed or removed at existing joints.
Where the apron meets concrete street paving, TxDOT's Houston District sheet DD-25 is one example. It calls for a saw-cut joint, breaking back the old pavement, and exposing and cleaning 18 inches of reinforcing steel.
In Beaumont, the code lets owners cut down the curb wall only as the city engineer directs. The city engineer also sets the driveway grade at no charge.
Three things get settled before forms go up: the opening width, the radius on each side, and the profile back to the property line.
Beaumont's driveway permit handout sets minimum widths by use. A home needs 10 feet, a one-way commercial entrance 15, and a two-way commercial drive 20. The city code caps commercial approaches at 35 feet.
The handout's minimum radii are 5 feet for residential, 10 feet for commercial, and 15 feet for commercial drives on arterial roads. The radius tangent point has to stay within the lot's property lines.
Near a corner, the code bars any curb cut within 30 feet of the extended curbline or edge of pavement. The handout states the same 30-foot minimum.
Spacing between drives is where the two differ. The code requires a safety island at least 20 feet wide between adjacent approaches. The handout lists 10 feet for residential, 20 for commercial, and 30 for commercial drives on arterials.
The handout carries no date, so confirm each figure with the Engineering Division before design.
Profile matters too. TxDOT's driveway grade guidance warns that abrupt grade changes slow vehicles to a crawl, inviting rear-end collisions and dragging the underside of a car. TxDOT and Beaumont's handout both cap residential drives at 12 percent.
On urban streets with short drives, TxDOT notes, profile vertical curves may not be practical. So the street-edge transition is shaped by hand, standard hand-form work for Hollier.
A new approach must never act as a dam. Gutter flow has to pass the opening at the same grade it had before the cut.
TxDOT's manual places a driveway's vertical curve at the projected gutter line, not closer to the travel lanes. The exception is a design with curb and gutter returns and proper drainage.
Where a radius return is used, the curb and gutter continue through it. TxDOT allows a gap there only for a curb ramp at a pedestrian or bicycle crossing.
Inlet location is the other check. TxDOT's Hydraulic Design Manual recommends against bypass flow, gutter water an inlet misses, upstream of driveways and intersections, because traffic would cross it.
On state highways, TxDOT's access management rules say side-ditch drainage shall not be altered or impeded. On Beaumont ditch streets, the city's survey crew sets culvert grade and pipe size after the permit is issued.
Street curb sits in the public right-of-way. Beaumont's handout notes that the city owns the street and the property on each side.
Beaumont requires a permit for any installation or removal in the public right-of-way. New or rebuilt approaches must be concrete or asphalt and follow the city's Chapter 14, Article 3.
Engineering approves the permit and the Building Codes Division issues it. The application includes a scaled drawing showing the drive width, property lines, and any existing drives on either side.
The abutting owner furnishes materials and labor for driveways and sidewalks. When a city road project destroys or alters an existing drive, the city replaces it.
Beaumont inspects each approach twice. The pre-pour visit checks dimensions, location, reinforcement, and forms. The post-pour visit comes after forms are stripped and cleanup is done. Book both through 311 or the Cityworks portal.
Work that closes part of a street also needs Beaumont's Street Cut and Barricading permit, filed through Cityworks.
Most approaches cross a public sidewalk, so plan the walk and the drive as one piece of work. Built together, their joints line up and they share one cure period.
Beaumont's handout gives the crossing its own rule. The part of the drive in line with an existing sidewalk matches the walk's width and carries a 2 percent cross slope.
Corner lots may add a curb ramp. Ramps are Hollier hand-form work, and Hollier also pours sidewalks, so all three can share one schedule.
A short checklist keeps the job moving from permit to pour.
In Beaumont, yes. The city requires a permit for any installation or removal in the public right-of-way, and street curb sits there. Other cities set their own rules, so check with your public works or engineering office first.
Yes. The crew removes curb beyond the current opening and rebuilds the added width with new radii. Beaumont's code bars changing a driveway's dimensions without a permit, so the permit comes first.
Saw-cutting works when the curb on either side is sound and still on grade. If the adjoining panels are cracked, settled, or holding water, replacing back to the nearest joints usually gives a cleaner, longer-lasting result.
It should not, as long as the gutter line is rebuilt at its existing grade. The flow line is surveyed before demolition, and the new gutter pan is set to match it so runoff keeps moving past the drive.
The first visit comes with forms and reinforcement set but no concrete yet. The inspector checks dimensions, location, reinforcement, and formwork. A second visit follows the pour, once forms are off and washout and cleanup are finished.
Both the handout and the city code put that on the owner of the abutting property, who furnishes the labor and materials. The handout adds culverts to the list. A city road project that destroys or alters a drive is the exception.
The city code allows no curb cut within 30 feet of the extended curbline or edge of pavement at an intersection. The city engineer may grant exceptions only for extreme circumstances where the public interest is served.
The code allows no more than two approaches on a tract with 100 feet of frontage or less. A tract with more than 100 but under 300 feet may have three.
Cure time varies with the mix, the temperature, and any rule the city or engineer sets. Beaumont's handout calls for driveway concrete that reaches 3,000 psi in 28 days. Hold off on traffic until your contractor says it is ready.
Yes. Hollier also pours sidewalks and flatwork, so the approach, the walk panel crossing it, and any curb ramp can be formed in one sequence. That keeps joints aligned and avoids a second mobilization.
City of Beaumont: Driveway Construction and Maintenance (Driveway Permit Information PDF, undated)
City of Beaumont Code (eCode360): Division 2, Sidewalk and Driveway Construction and Maintenance
City of Beaumont: Frequently Asked Questions, Public Works (Engineering)
TxDOT Roadway Design Manual: 16.3.1 Driveway Grades
TxDOT Access Management Manual: Drainage
TxDOT Hydraulic Design Manual: Carryover Design Approach
TxDOT Standard Sheet: Concrete Curb and Curb and Gutter (CCCG-22)
TxDOT Houston District Standard: Driveway Details (DD-25 (HOU))